Post 2025 Market Design – Capacity mechanism - Initiation
Publication date
Following National Cabinet's endorsement of the Energy Security Board's (ESB) final package of reforms, the ESB is carrying out further design work on the proposed capacity mechanism. This will include comprehensive consultation with all relevant stakeholders and interested parties, the outcomes of which will be used to help achieve the optimal design of the final model. The ESB has therefore released 2 papers:
- A scope of works document to provide stakeholders with more clarity about the approach and process that we intend to use to progress the design of a capacity mechanism.
- A project initiation paper, which outlines the main components of a capacity mechanism and the potential options, and gives stakeholders the opportunity to provide their views on these matters.
Submissions on the project initiation paper have now closed.
Further detail of stakeholder engagement opportunities will be published in early 2022.
The key milestones for the capacity mechanism detailed design process are set out below:
MILESTONE |
INDICATIVE TIMING |
Project initiation paper |
16 December 2021 |
Submissions due on project initiation paper |
10 February 2022 |
Detailed design consultation paper |
March / April 2022 |
Submissions due on consultation paper |
May 2022 |
Draft recommendations for detailed design |
August 2022 |
Submissions due |
September 2022 |
Submit proposed rule change to Energy Ministers |
Early December 2022 |