Energy assessment and management processes - Incitec Pivot Plant Gibson Island

Publisher
Department of Resources, Energy and Tourism
Date
Type

The Incitec Pivot plant at Gibson Island in Queensland used about 13 peta joules (PJ) of energy in 2008–09 in the manufacture of nitrogen-based fertilisers. This case study describes 3 projects estimated to save 150,000 giga joules (GJ) of energy annually. This case study was developed as part of the Energy Efficiency Opportunities (EEGO) program.